07/01/2025
6/11/2025
07/26/2025
07/04/2025
5/14/2025
6/2/2025
Construction of Learning Landscape, Phase I
The sloped lawn will be graded and leveled to form a flat and accessible surface, transversed by a wide and accessible concrete path throughout the landscape. Three multi-use seating zones will feature benches and fixed tables and chairs. The flagpole will be relocated.
As of July 28, 2025, construction of Learning Landscape (Phase I) is mostly complete. Seating and tables will be installed by September 2025.
The Learning Landscape project is grant-funded by New York State Aid for Library Construction, and was designed by CT Male Associates and Studio A Landscape Architecture and Engineering. Construction will be completed by The VMJR Companies of Glens Falls, NY.
After (almost)
6/3/2025
07/01/2025
The once-beautiful and manicured traditional landscaping installed in 1995 is difficult to maintain and has become overgrown. It no longer accentuates the building as it once did.
07/19/2025
07/03/2025
5/20/2025
During
07/25/2025
The Carnegie building's historic façade will be restored to visual prominence with the installation of complementary, sustainable, and low-maintenance landscaping. The building stairs will be removed and reconstructed; the pathway stairs and railing will be removed. The hardscaping materials will echo those used during the 1902 construction.
5/14/2025
07/19/2025
07/25/2025
07/26/2025
5/22/2025
Plans
The significant amount of lawn space on the west side is uneven and without function. It can not be actively utilized for Library or community activities.
Before
6/11/2025